Showing posts with label Wall Systems. Show all posts
Showing posts with label Wall Systems. Show all posts

Monday, October 4, 2010

Wall Covering Reboco


The wall finish is a 2 to 3 step process.  Much like cementatious applications in the U.S. (as opposed to synthetic) it is a three step process in most cases.  Above we see the chapisco (scratch coat) method where the looser mixture is flung against the wall to create a rough surface for bonding.  This is sometimes done by flinging the mixture through a screen 2cm x 2cm grid.  The second coat emboco is much like a brown coat and the third is the finish, reboco.

Week 10


Week 10.  The major task of week ten was finalizing the bond beam formwork and pouring the beam.  There were a variety of other task begun such as scaffolding construction and column surfacing.

Walls and Bond Beam Cage


Mercedes, Giorie, Pedreiro, and Servante worked on building up and weaving the walls while John, Ethan, and Julie installed the bond beam cages and James completed the fabrication of the structural trusses.  Walls that meet at corner or "T" conditions are woven together whereas every other course block laps the previous block perpendicularly.  Masons line and the plumb bob are the tools of choice for level and plumb and squaring the space is a matter of keeping an eye on the diagonal dimensions of the space. 

Friday, August 6, 2010

Wall Preparation



Week 8 brought with it four new people (Mercedes, Giorie, Dick, and Diane. Above - the finishing touches of the tijolinha foundation and the beginnings of the infill wall installations. At every third course of the tijolo (8 hole) wall system is a piece of 4/2 or 42 mm "rebar" (ferro)set in the mortar joint and drilled into the column. It is additional lateral support with the anticipation of childhood energy and futbols acting up against the parede (wall).

Tijolinha Header



The header system was initially intended to be the bond beam but was revised with the realization that there was going to be too much tela (screen) and it would demand additional un-needed mullion infrastructure to support it. The roof loads will continue to be transferred through the bond beam to the columns and the header height and structure for all openings has dropped to the 215 cm. The tijolinha header will have to support only itself and the small sections of wall above. Its' construction (as pictured above consists of a wood formwork (cut from off cuts of column form), two pieces of 3/8 or .8cm rebar that is buried in the first mortar joint (massa), two courses of tijolinhas (the smaller brick), and tijolos oito furros (8 holes) above with 4/2 rebar in the mortar joint. A plumb bob is used to check for plumb and dry line is set in each course level (nivel) and strait (reta). The initial header height is pulled from the FFE (Finish floor elevation) dry line and snapped across all coloumns.