Friday, June 15, 2012



WEEK FOUR

In week four the delays piled up, our team became smaller, yet we managed to get a fair amount accomplished once the materials did arrive to the site.  We poured a bond beam which was already formed, poured two slabs (one on grade and one as a ceiling), two retaining walls, poured the Second tier columns, and laid the brick foundation for the closet. We have begun to work long days (sometimes completing a pour before breakfast) due in part to losing a week because of delays.  The weather continues to be extreme.  Sometimes extremely hot and the mosquitoes continue to be crazy.  This has become somewhat stressful but all in all the quality and work ethic of the 2012 build crew has shown, literally working through the madness to prevail and hammer out lots of work in week four. 

No comments:

Post a Comment