Monday, June 28, 2010
Week 2-3
Between the visit to the construction site in Pocone and the arrival of more helping hands, we re-mason lined and water-leveled the entire site with respect to the finished floor elevation (FFE) of the existing house. This means we will need a lot of fill to get 4 cm (slab thickness) below the FFE but we cannot move the FFE because of the rising water levels during the wet season. While we were doing this, Ethan and Julie built a barbed wire fence around the entire site to keep the cows out, for once and for all (this is both to save our time of having to restring our lines but also for the safety of the cows as we begin to dig massive holes for the column footings). We also dug all 60 cm deep pier footings for all interior columns and began the trenches needed for the slab form work and moved a few electric poles out of our way (please note the OSHA-approved ladder in the picture).